CAT 2022 Slot 3 QA Question & Solution

ArithmeticEasy

Question

A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is

Options

150
23
36
140

Solution

Let the unit of work done by 1 man in 1 hour and 1 day be 1 MDH unit (Man Day Hour).

Thus, in 7 hours per day for 10 days, the work done by N people =$N\times\ 7\times\ 10$ MDH units.

Since this is equal to 35% of the total work,

35% of the total work = $N\times\ 7\times\ 10$ MDH units.

Total work = $\frac{\left(N\times\ 100\times\ 7\times\ 10\right)}{35}=200\times N$ MDH units.

The work left = $200N-70N=130N$ MDH units.

Now, 10 people left the job. So, the number of people left = (N-10)

Since (N-10) people completed the rest of work in 14 days by working 10 hours a day,

$(N-10)\times\ 14\times\ 10=130N$

$10N=1400$

N = 140

Thus, the correct option is D.